Yet another span was erected by connecting supports 6 and 7 in Yeniseysky district of the Krasnoyarsk Region, at the construction site of the Vysokogorsky Bridge, the construction project of which is included in Yenisey Siberia CIP.
The span installation in Yenisey river bed started in August, its length is 180 meters and its weight is more than 1300 tons. The next stage of work is the installation of the structure between the 7th and 8th supports.
The approaches to the bridge are being built at the same time. The slope protection works were completed, the culvert system was set up and asphalt was paved on the right bank. The slopes and illumination pole footings are being constructed on the left bank.
It should be noted that the length of the finished bridge will be almost 1200 meters and almost 2000 meters including approaches. The roadway will be two–lane, and the estimated traffic speed will be 80 km/h. The roadway of the bridge crossing will be illuminated, and the structure itself will be painted blue.
The northernmost bridge over the Yenisey River near the settlement of Vysokogorsky is the most important facility for the development of the transport infrastructure of the region. The Vysokogorsky Bridge will provide conditions for the implementation of investment projects to develop the Angara-Yenisey Economic District and are within Yenisey Siberia CIP. These include Polyus’s project for the construction of a new gold processing plant (GPP–5) at Blagodatnoye deposit, the project of Sovrudnik for the development of gold deposits in the Noyba area of Severo-Yeniseysky District of Krasnoyarsk Region, and the project of Amikan Mining Company for the development of the Veduginskoye gold deposit.