31 October 2023

The new tunnel will double the capacity of the Mezhdurechensk – Taishet section

A new rotary tunnel is being built on the stretch of the Krasnoyarsk highway Koshurnikovo – 570 km in the Kuraginsky district of the Krasnoyarsk Territory. This is a difficult section of the highway with a large height difference: the railway track here crosses the spurs of the Eastern Sayan and the mountain river Jeb. The work is being carried out within the framework of the investment project “Increasing the capacity of the Artyshta – Mezhdurechensk – Taishet section” included in the KIP “Yenisei Siberia”.

The tunnel will be laid parallel to the existing single–track I Dzhebsky tunnel built in 1964, which is now used to pass trains on the Mezhdurechensk – Taishet section. Specialists have already carried out a near-portal excavation, mounted a protective screen and started tunneling. The sinking is carried out by the mining method: drilling machines make holes in the rock, into which explosives are then laid. The crushed rock is transported to the surface using an underground dump truck. The total length of the new railway tunnel is 267 meters. Currently, 55 m deep into the rock massif has been passed.

The artificial structure will be one of the components of the project for the construction of the second main tracks on the Koshurnikovo – 570 km stretch. A total of 4.2 km of new roadbed will be laid here. In order to stretch the second tracks through the mountainous taiga terrain, the railway workers will build not only a tunnel, but also two new bridges with a length of 13 and 92 meters.

It is planned to complete the work and open double–track train traffic along the Koshurnikovo – 570 km stretch by the end of 2025. As a result of the project, the capacity of the Mezhdurechensk – Taishet section will double.