30 August 2022

The construction of access roads to the Vysokogorsky Bridge is being completed

In the area of construction of the Vysokogorsky Bridge, the project of which is included in Yenisey Siberia CIP, road workers are completing the construction of motorways for local residents to access the crossing. The new 10-km route will connect the Yenisey Route and public roads of the right bank of the Yenisey via the Vysokogorsky Bridge with.

The construction of the first section of the route – a bypass of the village of Vysokogorsky – has already been completed. This is almost 4 km of road, which will redirect heavy duty vehicles out of the village. The section ends with access to the Yeniseysk – Vysokogorsky motorway, the repair of which will start in autumn 2022.

The second section (6 km long) on the route Krasnoyarsk – Yeniseysk (271st km) – Vysokogorsky has been completed for almost 80% today. The construction of the road surface and the combined bridge over the Kostylevka River continues here. The floor slab of the bridge is made of reinforced concrete, and the spans are metal structures. The construction works here will be completed in October.

The northernmost bridge over the Yenisey River near the village of Vysokogorsky is the most important facility for the development of the transport infrastructure of the region. The Vysokogorsky Bridge will provide conditions for the implementation of investment projects to develop the Angara-Yenisey Economic District and are within Yenisey Siberia CIP. These include Polyus’s project for the construction of a new gold processing plant (GPP–5) at Blagodatnoye deposit, the project of Sovrudnik for the development of gold deposits in the Noyba area of Severo-Yeniseysky District of Krasnoyarsk Region, and the project of Amikan Mining Company for the development of the Veduginskoye gold deposit.