Segezha Group have launched the second construction stage of Xylotech Sibir fuel pellet plant five months in advance of the project schedule of the biotechnological complex construction at the manufacturing site of Lesosibirsky LDK No. 1 within the framework of Yenisey Siberia CIP.
The company’s project entails constructing a plant for advanced comprehensive processing of raw wood to produce cellulose and a wide range of other bio-products to be used as a substitution of subsoil resources and fuel. The new plant has increased the total pellet production capacity of the company up to 110.5 thousand tonnes of pellets per year.
The first construction stage of the third manufacturing line with an output of 30 thousand tonnes per year had been in progress from August to December 2019. As a result, the third pellet press with a capacity of 4.5 tonnes per hour was brought to operation.
The equipment for the second and final stage of the construction was received on March 3 this year. The team of Lesosibirsky LDK No. 1 started the installation as soon as the line constituent units had been delivered and unloaded. The work had been carried out for one month by the plant’s resources only, without disruption of the existing production process or deconstruction of any buildings. Representatives of Hekotek, the Estonian equipment manufacturer, participated in the construction.
According to the international certification results, the Siberian pellets were awarded the highest quality class, which brought the company to the European biofuel market. Currently, the biofuel is monthly shipped from Lesosibirsk to Baltic ports for further shipment to Denmark, Italy, Sweden and other European countries.
Source: segezha-group.com