Polyus, Russia’s largest gold mining company, has launched an advanced crushing complex, one of the key facilities of the fifth gold extraction plant (ZIF—5) of the Olympiadinsky Mining and Processing Plant under construction in the North Yenisei District of the Krasnoyarsk Territory. The new gold extraction plant is part of the Yenisei Siberia integrated investment project.
Polyus intends to complete the construction of ZIF-5 by the end of the year. The capacity of the new factory will be 8.3 million tons of ore per year. This will increase the total volume of primary ore processing at Blagodatnoye deposit to 17 million tons per year.
The technological scheme of the crushing complex begins with a receiving hopper and a gyration crusher, which grinds about 2,900 tons of ore per hour. This is followed by a transshipment and main conveyor with a length of more than one and a half kilometers. The ore is delivered to a warehouse with a capacity of up to 72,000 cubic meters. The chain is completed by a system of 8 plate feeders, which distributes the flows of crushed ore sent for primary processing.
The introduction of a crushing complex will increase the efficiency of controlling the granulometric composition of incoming ore due to the flexibility of the distribution of raw material flows. In addition, the introduction of a cyclic-flow technology for ore transportation (combining vehicles and a conveyor) will reduce the shoulder of ore delivery by dump trucks to a minimum, thereby significantly reducing fuel and fleet maintenance costs and improving the environmental performance of the enterprise.
The main part of the equipment of the new crushing complex is Russian-made. In particular, the main and transshipment conveyors were manufactured in Taganrog (Rostov region), and the car—weight conveyor was manufactured in Penza.
“The construction of ZIF-5 is Polyus’ main investment project in the Krasnoyarsk Territory today,” said Alexey Vereshchagin, Vice President for Capital Construction and Project Implementation at Polyus. – The commissioning of the crushing complex means that the factory is already more than 95% ready for launch. When ZIF-5 reaches its design capacity, it will increase gold production and significantly improve the economic performance of the Olympiadinsky Mining and Processing Complex.”