5 July 2023

Construction of two railway bridges has begun on the Mezhdurechensk – Taishet section

The Krasnoyarsk Railway has started the construction of two bridges over the Biryusa River and its Staritsa Effluent, located on the Mezhdurechensk –Taishet section connecting Western and Eastern Siberia. The engineering facilities were modernized as a part of the project included in Yenisey Siberia CIP and aimed at increasing the capacity of the Artyshta – Mezhdurechensk – Tayshet section.

The structures will appear on the Zapan – Tagul stretch as part of a large-scale work on the construction of second tracks here. Now it is a single-track section of the Russian Railways, running in difficult geographical conditions. It crosses the Biryusa River basin: its main channel, the Staritsa Effluent and the three-kilometer territory between them. Trains overcome this place by passing through two existing bridge crossings located on the same track one after the other.

Railway workers will build new bridges parallel to the existing ones, on the line of future second tracks. This will contribute to increasing export cargo flows in the direction of Far Eastern seaports and border crossings.

The length of the new bridges will be 365 meters across Biryusa (7 reinforced concrete spans) and 122 meters across Staritsa (4 metal spans). The total weight of the superstructures will be 2 thousand tons.

Currently, specialists have completed the first stage of construction: they fixed special pile structures on the bottom of the river. The next stage will be the construction of channel supports and coastal abutments. Next, the superstructures will be installed and the railway track will be laid on them on a reinforced concrete base.

The construction is scheduled to be completed in 2024.