23 October 2023

Construction of the second power unit of the Krasnoyarsk CHPP-3 switched to winter mode

Construction of the second power unit continues at Krasnoyarsk CHPP-3. The workers have already covered the end of the main building of the station with wall panels and moved on to installing the main and auxiliary equipment of the second power unit indoors. The construction of the power unit is carried out within the framework of the project to increase the capacity of the Krasnoyarsk CHPP-3, included in the KIP «Yenisey Siberia».

A heating system has already been installed in the turbine and boiler departments, the pumping station building, which will allow specialists to continue working throughout the winter. 727 people from 13 contracting organizations are involved in the construction site.

More than half of the installation work has been completed: 7.5 thousand tons of 13 thousand tons of metal structures and equipment are already ready. 41 units of equipment are used.

A tower cooling tower is also growing – a device designed to cool water with an air stream. Now the structure consists of five tiers out of the planned eight.

The second power unit of the Krasnoyarsk CHPP-3 is being built in order to provide the regional capital with additional thermal energy for further development. The project provides for a modern emission purification system: an electrofilter with a 99.9% efficiency of solid particles purification will be erected here – such SGC is currently installed at all urban thermal power plants. And the cooling tower under construction will reduce the thermal load on the reservoir and reduce the amount of water used by cooling and returning the resource to the technological process.

The construction of the second power unit is scheduled to be completed at the end of 2024. In total, about 27.5 billion rubles will be invested in the development of the Krasnoyarsk CHP-3.