Deputy Minister of Energy In Russia, Pyotr Konyushenko visited Krasnoyarsk CHPP-1 as part of the Siberian Energy Forum. In September of this year, modernization was completed at the station, which made it possible to increase the reliability of the equipment and reduce the burden on the environment. This investment project of the Siberian Generating Company (SGC) is included in the Yeniseiskaya Sibir CIP.
Three old chimneys were dismantled and a new one with a height of 275 meters was built at the operating enterprise without stopping the production of heat and electric energy, ensuring the dispersion of emissions in the upper layers, 15 modern electrostatic precipitators with a cleaning efficiency of over 99% were put into operation. In addition, Krasnoyarsk TPP-1 became one of the first enterprises in the country to introduce an automatic emission control system (SAC) certified by Rosprirodnadzor.
In addition, two boilers with a capacity of 220 tons of steam per hour each and two new turbines with a total capacity of 70 MW were put into operation at the station. The entire set of measures taken by SGK to upgrade Krasnoyarsk CHPP-1 has reduced the total emissions of the plant by 20%, and particulate emissions by 80%.
“The station, built during the Great Patriotic War, has been qualitatively transformed as part of a deep modernization using state support and regulatory mechanisms,” said Petr Konyushenko. – The Krasnoyarsk experience of comprehensive renovation of existing generating facilities is in demand and recommended for study in regions where there are issues of improving environmental efficiency and upgrading production facilities.”
According to Yuri Malyavkin, Chairman of the Board of Directors of SGK, the successful implementation of such a large-scale project was largely made possible by the cooperation of business and government.
Based on the materials of the sibgenco.online website
Cover photo: SGK Press Service